This sprint was completed on October 13, 2011. Most actions were tracked in Trac tickets.
Complete Quattor backlog is available here.
Completed Actions
Documentation
- Review/improve documentation for Quattor contributors (Devlopers' Corner)
Configuration Modules
- New ncm-spma migration strategy for QWG (Michel/Victor)
- Will be formally completed when the next QWG release is produced but already in trunk
gLite support
- glexec support on WN
- 7/7: done and committed
CDB
- Replace cake by a panc invocation through ant
- Story: ease integration of new Pan compiler version into CDB (dependencies managed by panc ant task used by SCDB and Aquilon), easier access to Pan options to control parallelism and serialization with a large number of profiles.
- Still some testing required with dependencies management but action only on CERN, no development required
SCDB
Monitoring
Miscellaneous
Actions still in progress after this sprint
Build tools
- Use of new build tools for all NCM components
- Depends partly on #258
- Target only 1 or 2 components as the first step
Configuration Modules
- ncm-network full rewrite
- Basic component ok, progressing...
- ncm-dpmlfc: rewrite without dabase-related functions and use ncm-mysql to configure the database (changes required in DPM/LFC templates)
- Direct mysql management removed, updating templates to use ncm-mysql
- ncm-gip2 should use perl-CAF to execute commands rather than `$cmd`
RHEL6/SL6 support
QWG
- Implement OS namespace improvement (Michel)
- vendor/version-arch or vendor/version/arch for OS templates
- Update CAF/LC to last versions (Michel)
- Agree on Pan annotation tags
- KVM support outside StratusLab (Jérome)
- Discuss with Cal what can be reused in configuration modules developped by StratusLab
gLite support
- CE tags publishing: fix for lcg-tags --sc
- CE configuration: allow different list of VOs on different CEs sharing the same gridmapdir
Monitoring
- Gather the information on existing Quattor-related probes at sites (Christos)
Web site
Actions Posponed
This actions have been moved back to the general backlog.
Build tools
SINDES
- Put it in Quattor repository (James/Jan)
- Planned after deployment of SNDES v2 in production at CERN (target date : Christmas 2011)
Last modified 13 years ago